Fort Calhoun had shut down for a scheduled refuel-ing outage before the flood. It remains in a safe shutdown condition pending NRC permission to re-start. Flood protection measures included sandbags, aqua berms and additional testing of emergency die-sel generators and loss of off-site power procedures. The NRC detailed additional inspectors to Fort Cal-houn during the peak of the flood, and NRC Chair-man Gregory Jaczko visited the plant to view the flood protection measures.
Cooper station used more than 5,000 tons of sand to create additional flood barriers. The plant continu-ously monitored the flood waters and coordinated with the Army Corps of Engineers regarding plans to release dams, but was not required to shut down the reactor since flood waters did not exceed technical specifications.